Martin Felux, civil engineer and industrial engineer
The monthly report of project management consists for the most part of material you already have: meeting minutes, programme, cost status, correspondence. With AI, a draft can be prepared from this that pulls together dates, costs and open points. What the situation means and what you recommend to the client is written by the project lead.
Reporting in project management
The AHO publication series, issue 9 (“Projektmanagement in der Bau- und Immobilienwirtschaft, Standards für Leistungen und Vergütung”), describes the service profile of project management. The publisher is the AHO, the German committee of engineers’ and architects’ associations and chambers on fee matters. According to its press release on the 2020 edition (as at March 2020), the profile has five fields of action: (A) organisation, information, coordination and documentation, (B) quality and quantities, (C) costs and financing, (D) dates, capacities and logistics, and (E) contracts and insurance.
The AHO now lists the issue on its website as at May 2025. A software vendor calls the 2025 edition the sixth edition in a blog post and describes the same five fields of action. That is a secondary source. According to the AHO website the publication costs 48.80 euros and I do not have it, so I have not checked the new edition against the original. I therefore mention the issue only as a reference and do not reproduce any further content.
How often you report and what the report must contain is governed by your contract. The structure along costs, dates, quality and contracts roughly matches the fields of the 2020 edition. Your client may ask for a different structure.
Structure of a monthly report
I propose this structure, which follows no standard: a summary for the client with status and need for decision, then the chapters Dates, Costs, Quality, and Contracts and variations, followed by the list of open decisions and the appendices. The chapters can be prepared from sources. The project lead writes the summary last, because it does more than summarise: it sets priorities.
- SourcesMinutes, programme, cost status, correspondence, frozen at the cut-off date
- Draft (AI)Structure, text and tables, every figure with source and status
- Assessment (you)Judgement, recommendation and signature of the project lead
Text version of the graphic
- Layer 1 from the bottom: Sources, Minutes, programme, cost status, correspondence, frozen at the cut-off date
- Layer 2 from the bottom: Draft (AI), Structure, text and tables, every figure with source and status
- Layer 3 from the bottom: Assessment (you), Judgement, recommendation and signature of the project lead
The sources
Every statement in the report should point to something that already exists. The table assigns chapter, source and division of tasks:
| Chapter | Source | The AI prepares | Stays with you |
|---|---|---|---|
| Dates | Programme, minutes | Compile deviations and stated causes | Assess the effect on the handover date |
| Costs | Cost status, checked invoices, variations | Fill the table, describe the development | Assess the forecast and reserves |
| Contracts | Correspondence, instructions, notices of hindrance | List with date and status | Position and recommendation |
| Open points | Minutes | Open decisions with the persons responsible | Weighting, what the client must decide |
How a meeting becomes minutes that work as a source is described in Meeting minutes with AI: from recording to sign-off.
Set a cut-off date on which the sources are frozen for the report, and state it in the report. Otherwise the draft contains Monday’s programme next to Friday’s cost status.
The HOAI (German fee regulations for architects and engineers) also lists programme, cost control and cost determination as basic services of site supervision in work stage 8 (Annex 10 no. 10.1, letters d, i and j, for buildings and interiors, in the version as at November 2026). So the building blocks of a report arise at points where documentation takes place anyway. The better the minutes and the cost status are maintained, the less has to be researched again for the report.
The draft
The AI reads the sources, assigns them to the chapters, summarises them and writes paragraphs in your template. It can fill tables with programme deviations and open points. An example with invented data:
The programme (as at 28 February) shows a deviation of two weeks against the baseline programme for the shell construction. Cause according to the minutes of 12 February: delayed delivery of the precast elements.
The sentence names source, status and cause. It does not say whether the handover date is at risk.
Figures only from checked sources
A language model produces text and does not calculate reliably, and it can produce values that sound plausible and are wrong. In its guidance on AI applications involving personal data, the Data Protection Conference (DSK) notes that providers of language models often state themselves that their texts make no claim to accuracy and should always be questioned. For the report this means: the software copies figures from the source file into the table, and the model writes only the text around them. Every figure carries a source and a status, as described for AI answers in general in Why AI answers need a source reference. A cost status that nobody has checked yet is marked as provisional in the report, or not used at all.
Before sending, you reconcile. A spot check is not enough if a figure has consequences: check every figure that the client uses for a decision against its source. The person who writes the report should not be the only one to check. A second person compares the figures with the sources, because your own text reads too smoothly.
A fixed template also helps the client. If dates, costs and open decisions are in the same place every month, changes are easier to spot. The draft must therefore always deliver the same chapters in the same order, even if a chapter occasionally contains only “no change”.
Checking steps before sending
The draft goes to the client only after these steps. The order is my suggestion:
- Cut-off date and status of the sources: does the same status apply to all chapters, and is it stated in the report?
- Figures: every figure that the client uses for a decision is checked against the source by a second person.
- Statements without a source: a sentence for which no source can be named is deleted or substantiated by the project lead.
- Consistency: does the summary match the chapters, for example on the date and on the cost status?
- Assessment and recommendation: the project lead writes both and signs.
How much time the draft saves
A monthly report in project management takes about 5 hours today. That is a figure from the author’s practice in project management and has not been measured. For the saving, the range that this website uses for reports and draft texts applies: 16 to 28 per cent. It covers only gathering the material and the draft. Checking and release stay with you.
The calculation: 5 hours are 300 minutes. 16 per cent of that is 48 minutes, 28 per cent is 84 minutes. A report then no longer takes 5 hours but 4.2 to 3.6 hours. The shorter figure of 2 hours per text in this website’s calculator stands for shorter reports and draft texts; a project management monthly report takes longer.
-
Lower range (16 %)48 minutes less per report
Today 5 hWith AI preparation 4.2 h -
Upper range (28 %)84 minutes less per report
Today 5 hWith AI preparation 3.6 h
Source: The author's assumption, not measured: 5 h from practice, 16 to 28 % saving as in this website's calculator
Text version of the graphic
- Lower range (16 %): Today 5 h, With AI preparation 4.2 h (48 minutes less per report)
- Upper range (28 %): Today 5 h, With AI preparation 3.6 h (84 minutes less per report)
- Source: The author's assumption, not measured: 5 h from practice, 16 to 28 % saving as in this website's calculator
Testing a draft
The simplest test uses your last report. Assemble the sources from the cut-off date at the time, have a draft produced and lay it next to your report. Then check where the draft deviates: are points missing? Do figures differ? Has the AI added something that is in no source? Every deviation shows where the template, the sources or the checking rule need improving. As a rule of thumb that I cannot substantiate: only when three reports in a row run through cleanly is it worth using it in a live project.
What stays with you
The assessment is the core of the report. Whether a deviation is a problem, how seriously to take a variation, which measure you propose and what the client needs to know first depends on the project, the contract and the relationship. An AI knows none of that. You also decide the tone in case of delay or dispute.
A sentence that only you can write (example with invented data): “The deviation in the shell construction does not endanger the handover date as long as the precast elements are delivered by the end of March. We recommend having the delivery commitment confirmed in writing.” It contains a judgement and a recommendation. Both presuppose that someone knows the supplier, the construction time and the contract.
The Federal Chamber of Engineers (Bundesingenieurkammer) writes on the use of AI: “When AI tools are used, it is always engineers who in the end take personal responsibility” (my translation). The sentence refers to AI-based services in engineering in general. In spirit it carries over to the monthly report, because the report goes out under your name.
Project data belongs on platforms that can be operated in line with the GDPR, that is in the EU or locally and with a data processing agreement. What matters in that agreement is covered in Data processing agreements for AI services: what to check. Consumer chat services are not a route for project data. Also check whether your contract with the client restricts passing on project documents. Your lawyer clarifies that, and your data protection officer clarifies the data protection questions.
What you can do now
- Mark every paragraph of your last report: source or assessment? The share shows what can be prepared.
- Decide which sources, with which status, may go into the report, and who releases them.
- Build a fixed template with unchanging chapters. Without one, every draft turns out different.
- Write down a checking rule for figures: which figure is reconciled against which source, and by whom?
General information, not legal or tax advice. Your tax adviser, data protection officer or lawyer will clarify the individual case.
Frequently asked questions
Can the AI write the monthly report completely?
It can prepare a draft from your sources. You write the assessment of the situation and the recommendation to the client yourself, because you sign and answer for it.
How do I make sure the figures are right?
Have figures taken over from the source file, not produced by the language model, and give the source and status for every figure. Reconcile them before sending, and have a second person check the figures that have consequences.
How much time does this save?
I have not measured anything. According to a figure from the author's practice in project management, a monthly report takes about 5 hours today. By this website's range, preparation saves 16 to 28 per cent of that, so 48 to 84 minutes, in gathering the material and in the draft. Checking and release stay with you. With your next report, measure how much time gathering, writing and assessing each take.
Sources
- AHO, Pressemitteilung zu Heft 9 „Projektmanagement in der Bau- und Immobilienwirtschaft“ (17.04.2020, Stand März 2020) (AHO press release on issue 9, project management in the construction and real estate industry) (retrieved on 13 November 2026)
- AHO, Schriftenreihe (Heft 9 mit Stand Mai 2025 aufgeführt) (AHO publication series, issue 9 listed as at May 2025) (retrieved on 13 November 2026)
- Blog eines Softwareherstellers zur 6. Auflage von AHO Heft 9 (Juli 2026, Sekundärquelle, nicht am Heft geprüft) (blog of a software vendor on the 6th edition of AHO issue 9, July 2026, secondary source, not checked against the publication) (retrieved on 13 November 2026)
- Bundesingenieurkammer: Verantwortung von Ingenieurinnen und Ingenieuren im Zeitalter Künstlicher Intelligenz (Mai 2025) (Federal Chamber of Engineers: responsibility of engineers in the age of artificial intelligence) (retrieved on 13 November 2026)
- DSK-Orientierungshilfe „Künstliche Intelligenz und Datenschutz“, Version 1.0 vom 6. Mai 2024 (Abschnitt 3.3 Ergebnisse auf Richtigkeit prüfen, Rn. 64) (guidance of the Data Protection Conference, section 3.3 on checking results for accuracy, margin no. 64) (retrieved on 13 November 2026)
- HOAI Anlage 10 Nr. 10.1 (geltende Fassung), Leistungsphase 8, Buchstaben d, i und j (Terminplan, Kostenkontrolle, Kostenfeststellung) (HOAI annex 10, work stage 8, items d, i and j: programme, cost control, cost determination) (retrieved on 13 November 2026)